Water Abstraction Licence Applications

What the Environment Agency expects to see, how long it really takes and how to put together an application that gets through first time.

Do you need an abstraction licence?

If you take more than 20 cubic metres of water a day from a river, reservoir, canal or aquifer in England, you almost certainly need a licence from the Environment Agency. That is roughly 4,400 gallons, which is less than many people expect.

The forms themselves are not the hard part. What decides an application is the evidence behind them: whether you can show the abstraction will not harm the river, other water users or protected sites and that the volume you are asking for is justified.

This page sets out the process as it works in practice. It draws on the Environment Agency guidance and on hands-on experience of licensing and permitting for water companies and reservoir owners, including Strategic Resource Option (SRO) schemes.

20 m³/dayThe threshold above which a licence is needed.
28 daysAbstracting for longer than this needs a full licence rather than a temporary one.
4 monthsThe standard decision period for a full licence. Complex cases often run longer.
6 to 18 yearsThe usual life of a new licence, set to line up with other licences in the catchment.

Which licence do you need?

The type of licence decides which application forms you complete. Almost every application starts with Part A, which covers who you are, and most include Part E, which works out the charge.

Full abstraction

Taking more than 20 m³ a day for 28 days or more, from surface water or groundwater.

Parts A, B, C and E

Transfer

Moving water from one source to another without using it in between, for example from one reservoir to another.

Parts A, B, C and E

Temporary

A one off abstraction of less than 28 days that is not part of a repeating activity.

Parts A, B, C and E

Impoundment

Building or altering a dam, weir or sluice that holds back the flow of inland water.

Parts A, D and E

Variation

Changing an existing licence: a new abstraction point, a new purpose, different timing or more water.

Parts A, B, C and E

Renewal

Replacing a licence that expires within the next 12 months. Apply at least three months before it ends.

WR327, or A, B, C and E with changes

How an abstraction licence application works

Most of the effort goes in before anything is formally submitted. The pre-application response tells you what evidence the Environment Agency wants to see, and the rest of the programme is built around answering it.

How long does it take?

Longer than most people plan for. The four month decision period only applies once the application has been submitted, and the work to get there is usually the bigger part of the programme.

A straightforward licence with a clear case and few environmental sensitivities can be done in under a year. Transfers, public water supply schemes and anything near a protected site are a different matter. Two to three years from first contact to decision is common, and larger schemes can take longer still.

The things that usually stretch the programme are:

  • Survey seasons. Ecology and fish surveys can only be done at certain times of year, so missing a window can cost twelve months.
  • Agreeing the data. Flow records, modelling assumptions and baselines often need several rounds with the Environment Agency before they are accepted.
  • Consultees. Natural England, Habitats Regulations assessments and advertising all add time during determination.
  • Other permits. A discharge permit, impoundment licence or planning consent can hold up the whole scheme.
  • Information requests. Each request after submission means updating the evidence, and decisions on complex cases often take longer than four months.

A complex scheme

Indicative, in months
Scoping and engagement
Pre-application
Evidence and surveys
Other permits
Pack, sign off, submit
Determination
061218243036
3 monthsLatest point to apply for a renewal before the licence expires. Miss it and it is treated as a new application.
12 monthsMinimum right of access to the abstraction land from the licence start date.
28 daysWindow to appeal a decision or to appeal if no decision is made in time.

What goes in an abstraction licence application

The forms ask the questions and the supporting documents answer them. These are the pieces that make the difference between an application that goes straight through and one that comes back with questions.

The cover letter

The first thing the assessor reads and their guide to everything else
+

The forms are rigid. The cover letter is where you explain the context, set the scope and deal with any grey areas before the assessor finds them. On a well run application it is built directly from the register of pre-application responses.

What it covers

  • What is being applied for and why it is needed
  • The pre-application reference and anything that has changed since
  • A response to every point raised at pre-application, with a pointer to the evidence
  • What is in scope and what is not, with the reason
  • A list of every enclosed document

Where it earns its keep

  • Explaining why a hands-off flow should or should not apply
  • Clarifying form answers that do not fit the tick boxes
  • Justifying a licence period outside the normal range
  • Flagging other permits being applied for in parallel

Environmental Assessment Report (EAR)

The main evidence that the abstraction will not cause environmental harm
+

Part B asks whether you need a full Environmental Impact Assessment or an environmental appraisal. Where a full EIA is not required, the appraisal normally takes the form of an Environmental Assessment Report: one document that brings together the baseline, the predicted effects and the mitigation.

Typical contents

  • Description of the scheme and its zone of influence
  • Hydrology: flows, levels and water balance with and without the abstraction
  • Water quality, ecology, fish and geomorphology baseline
  • Water Framework Directive compliance assessment
  • Habitats Regulations screening for designated sites

Often asked for as well

  • Effects on other abstractors and protected rights
  • Invasive non native species risk, particularly for transfers
  • Climate change and resilience in a severe drought
  • Mitigation, monitoring and how uncertainty is dealt with

Emergency and contingency planning

How the abstraction will be run when things do not go to plan
+

This is not a named section of the application forms, but it is good practice. Showing how the environment is protected in a drought, a pollution incident or an equipment failure strengthens the case for the conditions you are asking for.

  • Drought operation: triggers, control curves and when abstraction is reduced or stopped
  • Low flow protection: hands-off flows or compensation releases that must be kept up
  • Pollution incidents: who shuts the intake and how quickly
  • Equipment failure: pumps, screens and meters, with backup and repair arrangements
  • Biosecurity: stopping invasive species spreading through a transfer
  • Communication: named contacts and how the Environment Agency is told

Maps and plans

The Environment Agency guidance stresses supplying a map to avoid delays
+
  • Every abstraction point, reach or area, using the same names as the forms
  • A full 12 character national grid reference for each point
  • The land where the water will be used
  • Any proposed reservoir or storage
  • Every discharge point
  • The boundary of the land you own or have access rights over

Justifying the volume

Showing the amount asked for is reasonable
+
  • How the annual, daily, hourly and peak rates were worked out
  • Why the daily maximum may be more than the annual total divided by 365
  • How much water, if any, is reused
  • Water efficiency measures and water saving equipment
  • For water companies, the link to the Water Resources Management Plan and the benefit to deployable output

Access rights and other evidence

Proof you can lawfully reach the water and records of who you have spoken to
+
  • Proof of ownership, a lease, deed of grant or tenancy or the negotiations so far
  • Planning permission status and expected date
  • Evidence of discussions with the local fisheries team on eel screening
  • Correspondence with Natural England and any management agreement
  • Details of any licence aggregation or water rights trade

How we structure an application

On larger schemes the answers sit with several people: the applicant, the operator, engineers, ecologists and landowners. Two simple registers keep track of who owns what and make sure nothing goes to the Environment Agency unanswered.

FormRefQuestionStatusAnswer or sourceActionOwner
AA3.2Company registration numberAnsweredCompanies HouseNonen/a
BB10.1Abstraction location and grid referenceOpenEngineering drawingConfirm 12 character NGREngineer
BB13.1fMaximum daily amount (m³)OpenOperational modellingConfirm peak daily rateOperator
CC4.1cMeasurement methodAnsweredOutline design reportCheck design is currentOperator
EE2.2Water availability statusTo checkGov.uk mapping toolCheck status at the NGRFWC
Forms question tracker. Every question on Parts A, B, C and E: whether it can be answered yet, where the answer comes from, what is still outstanding and who owns it. A running count of open actions per party shows quickly where things are stuck.
#TopicEnvironment Agency requestResponseEvidenceOwnerIn cover letter
1Downstream water availabilityAssess the effect on downstream catchmentsCovered in the hydrology chapterEARFWCYes
2Compensation flowsReview the current compensation regimeHydraulic assessment completedTechnical noteFWCYes
3Invasive speciesAssess transfer risk and mitigationRisk assessment in progressINNS reportEcologistPending
4Drought resilienceShow resilience to a severe droughtModelled under design droughtModelling reportOperatorYes
Pre-application response register. Each point from the pre-application letter, how it has been answered, where the evidence is and whether it has made it into the cover letter. This register becomes the backbone of the cover letter. Rows shown are illustrative.

Alongside these sits a short permitting engagement strategy: the overall approach, the key people and their roles, the programme of Environment Agency reviews and meetings and a live log of risks and issues. It keeps everyone working to the same dates.

Abstraction licence application checklist

Work through each part of the application form. Ticks are not saved, so print the list if you want a copy to work from.

Planning an abstraction or transfer licence?

FWC can help at any stage, from early scoping and pre-application through to the evidence, the forms and the cover letter.

Discuss your application

Where FWC fits in

Licence applications draw on hydrology, ecology, engineering and regulatory knowledge, and they need someone to hold it all together. That is the role FWC usually plays.

FWC has worked on the permitting of Strategic Resource Option (SRO) schemes, the large water company projects that move through the RAPID gated process. That work covered permitting engagement strategies, pre-application evidence, form and response tracking and coordination between water companies, consultants and the Environment Agency to get schemes regulator ready.

  • Licensing strategy and early engagement with the Environment Agency
  • Permitting support for SRO and other large water resources schemes
  • Hydrological modelling, water balances and drought resilience
  • WFD assessment and input to the Environmental Assessment Report
  • Question trackers, response registers and coordinating all parties
  • Completing the forms and drafting the cover letter

This guide is based on Environment Agency guidance notes WR329, WR331, WR333 and WR391 and the gov.uk guidance on applying for a water abstraction or impoundment licence. Forms and charges are updated regularly, so always check the current versions on gov.uk. It is general guidance, not legal advice.